Mallaig Passenger Ferry Pontoon
Harbour Engineers Wallace Stone issued the Completion Certificate for the Passenger Walkway Pontoon on Friday 4th April 2019 signifying that contractors Gael Force Engineering had completed the project at a cost in the region of £193,000.
Mallaig Harbour Ice
Several weeks behind schedule it may have been but on Friday 5th April half a dozen fishing boats took on board ice from the new Harbour Authority owned Mallaig Ice Plant.
The new plant has not yet been fully commissioned and questions remain about it’s overall ability to provide ice at the touch of a “computer button” but progress is being made, ice is being manufactured and delivered to fishing vessels although currently its only available during office hours on week days at present.
Service will be improved once the IT side of the operation is in situ
Robert MacMillan
CEO