Harbour News – May 2019

By News No Comments

Mallaig Passenger Ferry Pontoon

Harbour Engineers Wallace Stone issued the Completion Certificate for the Passenger Walkway Pontoon on Friday 4th April 2019 signifying that contractors Gael Force Engineering had completed the project at a cost in the region of £193,000.

Mallaig Harbour Ice

Several weeks behind schedule it may have been but on Friday 5th April half a dozen fishing boats took on board ice from the new Harbour Authority owned Mallaig Ice Plant.

The new plant has not yet been fully commissioned and questions remain about it’s overall ability to provide ice at the touch of a “computer button” but progress is being made, ice is being manufactured and delivered to fishing vessels although currently its only available during office hours on week days at present.

Service will be improved once the IT side of the operation is in situ

Robert MacMillan

CEO

01687 462154

info@mallaigharbourauthority.com   

Harbour News – April 2019

By News No Comments

Passenger Walkway

The new Passenger Access Walkway is now operational.  It began it’s working life on Friday 22nd March – several weeks behind schedule.

Contractors Gael Force Ltd have now completed 99% of the work with the only outstanding item being the replacement of ill fitting mesh panelling with ones manufactured/cut to the proper size.

As an add on to the contract mesh infill panels will be fitted between the walkway ramp and the pier surface.

Mallaig Harbour Ice

The plant is now powered up and the electrical meters were fitted on Thursday 28th March after what seemed an interminable delay.

Officials from TRS Ltd will be on site week commencing 8th April so hopes are high that the new Plant will become operational later this month.

Robert MacMillan

CEO