Fish Quay
Contractors Gareloch Support Services (GSS) have now completed all scheduled works on the Mallaig Fish Quay. Repairs to walings, ladders and the wooden piling have all taken place in the £450,000 contract.
Jarys Wharf
GSS have also been requested to insert two new wooden piles and a new ladder at the “Spanish John” berth on Jary’s Wharf and this is currently being carried out. Completion date in early March.
Outer Harbour
Local divers have been busy in the Outer Basin clearing some debris/rocks that have accumulated on the seabed over the past few months.
Loch Fyne
MV Loch Fyne is set to arrive in Mallaig on Friday 3rd March in order to take up the Mallaig-Armadale ferry run as scheduled on Friday 31st March – the commencement date of the 2017 summer season.
Robert MacMillan
CEO